Kentucky approves 482MW power agreement for TeraWulf data campus
Image: DCD The Kentucky Public Service Commission approved a 482MW electrical service agreement for TeraWulf's planned Justified Data Campus in Hancock County. TeraWulf will bear market, transmission, delivery and customer-specific infrastructure costs, as well as credit-support obligations, under the agreement. The project will use an existing 482MW grid connection. The first facility on the former aluminum-processing site is due online in 2027.